Procurement & Timeline


A phased programme of delivery

MAHP will be delivered in phases over the next five years and beyond, with sites progressing through design, planning and procurement in coordinated batches. The first nine schemes are already well advanced, with planning submissions taking place during 2026 and procurement expected to begin from August. Further batches will follow over the next six to nine months, creating a continuing pipeline of opportunities as sites move from feasibility and concept design into planning and delivery.

Procurement

The procurement process will comprise of a selective stage and a tender stage, shortlisting 5/6 companies utilising the Competitive Flexible Process under the Procurement Act (PA) 2023.

This will incorporate some dialogoue covering the following areas amongst others.

  • Legals

  • Program and Programme delivery

  • Commercials

  • Pricing Mechanism

  • PCSA comprising

Timeline

Phase

Task

Start Date

End Date

PSQ Period

PSQ Period

05/08/2026

24/08/2026

PSQ Clarifiation Period

05/08/2026

19/08/2026

PSQ Submission Date

24/08/2026

PSQ Evaluation Period

24/08/2026

07/09/2026

PSQ Shortlisting Outcome Letters Issued

08/09/2026

ITT Period

ITT Period

09/09/2026

02/12/2026

ITT Clarification Period

09/09/2026

18/11/2026

ITT Submission Date

02/12/2026

ITT Evaluation Period

03/12/2026

24/12/2026

ITT Internal Approvals Deadline

24/12/2026

09/02/2027

Contract Award

Contract Award Notice and Tender Outcome Letters Issued

10/02/2027

Standstill Period

10/02/2027

19/02/2027

Contract Award / Signing Date

19/02/2027

10/03/2027

Mobilisation Period

10/03/2027

19/04/2027

Contract Start Date

19/04/2027

N.B. This timetable is indicative only and may change